Initial Key Milestones in Decommissioning Process

Key Milestones

June 7, 2013 SCE announces it will permanently retire San Onofre Units 2 and 3.
June 12, 2013 SCE notifies the NRC it has permanently ceased operation of Units 2 and 3.
July 2013 SCE transfers fuel from San Onofre Unit 2 reactor to the spent fuel pool, triggering a federal license change to an NRC possession license from an NRC operating license.
Sept. 26, 2013 NRC holds Public Meeting on Decommissioning Process.
Sept. 23, 2014 SCE files Post-Shutdown Decommissioning Activities Report (PSDAR), Decommissioning Cost Estimate and Irradiated Fuel Management Plan with the NRC.
Oct. 27, 2014 NRC conducts public meeting regarding PSDAR in Carlsbad, Calif.
Dec. 2014 SCE awards Independent Spent Fuel Storage Installation contract.
June 2015 NRC approves changes to San Onofre emergency planning requirements.
Oct. 2015 California Coastal Commission approves Independent Spent Fuel Storage Installation expansion.

Guiding Principles

Safety, stewardship and community engagement will guide the Decommissioning process.