You are using an outdated browser. Please upgrade to the latest version for the best experience. Upgrade your browser now.

Aug. 3, 2018 Canister Loading Incident – Key Information and Background

What happened?

On Aug. 3, 2018, during the placement of the 29th MPC, the MPC came to rest on the top of a component of the CEC called the divider shield ring, and against the inside surface of the Hi-TRAC (Holtec International Transfer Cask). The Vertical Cask Transporter (VCT – mobile crane) slings supporting the canister went slack indicating the MPC was hung-up. The crane operator could not see the MPC (because this is an operation commonly called a blind lift) and a spotter assigned to observe the MPC did not recognize the slack sling condition.

Canister Wedged 1

 

Canister Wedged 2

Key oversight personnel were located 150 feet away in a low radiation dose area observing the slings from the rear of the VCT and believed, because the slings appeared to be taut, that the MPC was being lowered to the bottom of the CEC. However, elevated radiation measurements taken near the VCT indicated that the canister had not been fully lowered to the bottom of the CEC. Actions were initiated immediately to raise the VCT, lifting the canister off the divider shell ring, thereby placing the canister load back on the slings. The canister was subsequently realigned and lowered successfully to the bottom of the CEC.

SCE then stopped all canister-loading activities and subsequently notified the Nuclear Regulatory Commission. (Read more in the Licensee Event Report, submitted to the NRC).

San Onofre personnel implemented appropriate immediate corrective actions. These included restoring the control of the load to the rigging and lifting devices, properly placing the canister in the storage vault, suspending all movement of spent fuel, and initiating an investigation of the event.

– Nuclear Regulatory Commission, Event Summary, Preliminary Finding

The health and safety of employees and the public was never, and would never have been, impacted by this event due to the robust construction of the canister. The drop analysis, validated by an independent expert and provided to the NRC, confirms canister integrity would not have been breached had a drop occurred.


1 ISFSI Pad MPC Inspctn_MP17557

NRC Special Inspection

On Sept. 10, a team from the NRC began an onsite inspection at SONGS. The inspection charter can be found here.

In October, the NRC posted its preliminary findings to its website. The NRC was critical of SCE and noted myriad deficiencies in the fuel transfer operation program, including the areas of training, procedures and oversight.

On Nov. 8, the NRC held a three-hour webinar to update the public on its preliminary findings, outline potential violations committed by SCE, and answer questions from citizens. The webinar slides are available here.

Read our statement on the NRC’s webinar here.

The NRC’s final inspection report is available here.


Process Improvements
The graphic above illustrates the areas of Fuel Transfer Operations where improvements have been made.

The path forward

Following the incident, SCE pledged to not re-start spent fuel transfer operations until satisfied all corrective actions are in place and proven effective, the public has been briefed, and the NRC has completed its onsite inspection actions.

So what have we been doing over these past several months?

Much of the work has been to identify gaps in training, procedures and how we do oversight. Our vendor has been taking a hard look at their processes and taken the following corrective actions:

  • Revised procedures with enhanced details

  • Implemented a revised training program

  • Increased staffing to ensure proper management and support

  • Implemented additional load monitoring technology

  • Implemented a lower threshold for taking corrective actions which helps with problem identification and resolution

We have also taken steps to improve the way we do oversight:

  • Implemented changes to ISFSI project management

  • Revised training for oversight personnel

  • Increased oversight personnel with dry fuel canister loading experience

  • Will provide more effective oversight of ISFSI loading activities and oversight personnel effectiveness, when fuel transfer operations begin again

Before actual fuel transfer operations begin, we will conduct a series of readiness reviews with the internal team, as well as an independent assessment of readiness. On top of these reviews is the NRC’s review to ensure we are, indeed, ready for re-start.

The bottom line is, we will resume fuel transfers only when we are positive we can do so safely, correctly and without incident. That is our commitment.

Please join us at the Community Engagement Panel meeting Nov. 29 to learn more.

Copyright © 2018 Southern California Edison. All Rights Reserved. PRIVACY NOTICE