NRC Inspection Reports
The decommissioning process is conducted under the oversight of the Nuclear Regulatory Commission. The NRC routinely conducts inspections that cover various aspects of decommissioning, including dismantlement activities, dry fuel storage of spent nuclear fuel, and security.
Below are the completed NRC inspection reports, beginning in the fourth quarter of 2019, when plant became an ISFSI-only site and demolition activities commenced. Previous inspection reports can be found on the NRC website.
| Year | Inspection Reports |
| 2019 | 2019007 & 2019002 ISFSI |
| 2020 | 2020001; 2020002; 2020003 ; 2020004; 2020005 & 2020001 ISFSI; 2020006 & 2020002 ISFSI; 2020007 & 2020003 ISFSI; 2020401 |
| 2021 | 2021001; 2021002; 2021003; 2021004; 2021402 |
| 2022 | 2022001; 2022002; 2022003; 2023004; 2022005; 2022006 |
| 2023 | 2023001; 2023002 & 2023001 ISFSI; 2023003; 2023004; 2023005; 2023006 |
| 2024 | 2025001; 2025002; 2024003; 2024004; 2024005; 2024006 & 2024001 ISFSI |
| 2025 | 2025001; 2025002 |