(Coastal) California Coastal Commission - CDP 2015 Addendum
Please refer to paragraph 2 on page 9 of 12 (pdf page 9 of 377) for Coastal Commission’s conclusions regarding groundwater contacting the bottom of the ISFSI. Here it concluded that “Increases in the water table elevation related to sea level rise could potentially lead to intermittent ... groundwater contact with the base of the ISFSI toward the end of the proposed 35-year life of the project. However, the design of the ISFSI is such that there are multiple barriers, including the 3-foot thick foundation pad and the steel cavity enclosure container (CEC), between the groundwater and the fuel storage casks, and limited contact with groundwater would not undermine the structural integrity of the ISFSI during the proposed project life.”